WEYE3 Improvements to the Recycler/Main Injector to Deliver 850 kW+ 578
 
  • R. Ainsworth, P. Adamson, D. Capista, N. Chelidze, K.J. Hazelwood, I. Kourbanis, O. Mohsen, D.K. Morris, M.J. Murphy, M. Wren, M. Xiao
    Fermilab, Batavia, Illinois, USA
  • C.E. Gonzalez-Ortiz
    MSU, East Lansing, Michigan, USA
 
  The Main Injector is used to deliver a 120 GeV high power proton beam for Neutrino experiments. The design power of 700 kW was reached in early 2017 but further improvements have seen a new sustained peak power of 893 kW. Two of the main improvements include the shortening of the Main Injector ramp length as well optimizing the slip-stacking procedure performed in the Recycler to reduce the amount of uncaptured beam making its way into the Main Injector. These improvements will be discussed in this paper as well future upgrades to reach higher beam powers.  
slides icon Slides WEYE3 [24.715 MB]  
DOI • reference for this paper ※ doi:10.18429/JACoW-NAPAC2022-WEYE3  
About • Received ※ 02 August 2022 — Revised ※ 08 August 2022 — Accepted ※ 10 August 2022 — Issue date ※ 18 August 2022
Cite • reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml)